Published: 2012-05-28
Last updated: 2022-03-18
A clearly structured project claim analysis is most helpful for the profound understanding of a claim situation, and thus, in determining the best claim strategy.
We pick up the claim case of sub-section Project Claim Management. In that case, we have two parties involved:
A and B have a contract under which B has to provide engineering, design, manufacturing, delivery, installation and commissioning of a storage control system (SCS), following a schedule of twenty four months with eight major milestones.
On 14. October, the project manager of B calls John, an independent claim consultant, to help with a pending claim against A and with their project claim analysis.
Two days later, John begins to work on the case. Between 16. and 20. October, he carries out interviews with all involved employees of B in order to get an overview and documents his findings for his later project claim analysis report:
12. September, 09:30 am: Sixteen months into the project, B is scheduled to deliver the SCS equipment and needs access to the project site which is under control of A. The entrance to the site is blocked by a twelve-meter container. The driver of the truck with the SCS equipment parks next to the container and calls the project office of B for further instructions.
12. September, 09:40 am: Within ten minutes, the chief engineer of B decides to setup an improvised access gate thirty five meters east of the original one and immediately sends a team of four workers and the necessary material to site in order to carry out the works. In an internal note, the chief engineer of B explains he has to take fast decision and action in order to ensure milestone M6 which corresponds to the successful installation of the SCS equipment.
12. September, 14:40 am: Five hours later, the improvised access gate is finished and B delivers the SCS equipment and the installation team continues with system installation so that they can keep the corresponding performance milestone M6.
10. October: Five weeks later, together with the performance documentation of milestone M6, B informs A by sending a notification about the improvised access gate, together with an invoice asking for payment of an extra EUR 8,000.-- for the setup of this gate which, by the way, is continuously used by the employees of A and other suppliers ever since it was installed.
After concluding all the interviews, John analyses the contract and finds these specific contract clauses that might be relevant for the project claim analysis:
Clause (3.1): The employer shall give the contractor
right of access to, and possession of, all parts of the site. The right and
possession may not be exclusive to the contractor.
Clause (5.2): The contractor shall be responsible for
the adequacy, stability and safety of all site operations, of all methods of
construction and of all the works.
Clause (6.3): During the
execution of the works, the contractor shall keep the site free from all
unnecessary obstruction.
Clause (7.1): The contractor shall, whenever required
by the employer, submit details of the arrangements and methods which the contractor
proposes to adopt for the execution of the works. No significant alteration to
these arrangements and methods shall be made without this having previously
been notified to the employer.
Clause (7.9): The contractor shall give the employer
not less than 7 days’ notice of the date on which any plant or a major item of
other goods will be delivered to the site.
Clause (8.2): Unless the employer, within 7 days
receiving a project time schedule, gives notice to the contractor stating the
extent to which it does not comply with the contract, the contractor shall
proceed in accordance with the project time schedule, subject to his other
obligations under the contract.
Clause (8.4): The contractor shall be entitled (…) to an extension of time for completion and/or additional payment if and to the extent that completion (…) is or will be delayed by any of the following causes:
(a) (…)
(b) any
delay, impediment or prevention caused by or attributable to the employer, the employer’s
personnel, or the employer’s other contractors on the site.
Clause (18.1): If the contractor considers himself to
be entitled to any extension of time for completion and/or additional payment, (…),
the contractor shall give notice to the employer, describing the event or
circumstance giving rise to the claim. The notice shall be given as soon as
practicable, not later than 28 days after the contractor became aware, or
should have become aware, of the event or circumstance.
Clause (18.2): Within 28 days after the contractor
became aware (or should have become aware) of the event or circumstance giving
rise to the claim, (…), the contractor shall send to the employer a fully
detailed claim which includes full supporting records of the basis of the claim
and of the extension of time and/or additional payment claimed.
Clause (18.3): Within 28 days after receiving a claim
or any further records, the employer shall respond with approval, or with disapproval
and detailed comments.
Clause (18.7): Disputes shall be handed over to an
Independent Expert, jointly appointed by both parties, within 28 days after one
party gives notice to the other party of its intention to refer a dispute to an
Independent Expert.
Clause (18.9): Unless settled amicably, any dispute in respect of which the Independent Expert’s decision (if any) has not become final and binding shall be finally settled by international arbitration.
With this preparation, John turns to the actual project claim analysis. He checks the project documentation for all available project records in order to find out if there is sufficient evidence to support the claim. He finds five documents, other than the contract between A and B. The following time line diagram summarizes the available evidence, from the perspective of B. This diagram forms the core of the project claim analysis. Please note that John only refers to the hard evidence.
Time |
A |
|
B |
10. May (last
year) |
|
<-------------> |
|
|
|
Contract |
|
|
|
|
|
12. Sept. |
|
B1
>< |
|
|
|
Internal
Notification of B Chief engineer
informs the project manager: gate is blocked; we build an improvised
access gate to keep the schedule. |
|
|
|
|
|
12. Sept., 15:00 |
|
<--------------
B2 |
|
|
|
Delivery note SCS equipment
delivered |
|
|
|
|
|
10. Oct. |
|
<--------------
B3 |
|
|
|
Invoice /
notification Partial payment
for milestone M6, including M6 performance documentation and the
notification of installation of an improvised access gate for EUR
8,000.— |
|
|
|
|
|
10. Oct. |
|
A1
-------------> |
|
|
|
Confirmation Delivery of SCS
equipment accepted |
|
|
|
|
|
14. Oct. |
|
A2
-------------> |
|
|
|
Payment
notification Notification
that payment for milestone M6 was transferred, EUR 8,000.— for the
improvised gate not included |
|
John calls the project manager of B to inform him of the results of his project claim analysis and asks for a meeting to discuss if B has sufficient evidence for a claim and to decide further steps.
In the following meeting John emphasizes again that his project claim analysis only contains project records that count as hard evidence. After a short discussion, they come to the conclusion that B does not have sufficient evidence for a claim so far, subject to further correspondence with A.
Reasons:
This example shows that a project claim analysis which only considers records that provide hard evidence is very critical and therefore, can help to avoid unnecessary arguments between contract parties. It also shows how important it is to regularly check the project site for any obstacles and closely coordinate with the other involved or affected parties before making large deliveries.
Return to Project Management Case Studies
Return from Project Claim Analysis to Home Page
|
|
Your Comments
Have your say about what you just read! Leave me a comment in the box below.